Roundabout Traffic Patterns for Golden Gate Point

On December 16, 2020, the Florida Department of Transportation (FDOT) held a public meeting via Zoom about the roundabout at US 41 and Gulfstream which left many questions unanswered for residents of Golden Gate Point. After that meeting, the GGPA contacted FDOT to ask for a public meeting applicable to GGP for all GGP residents. Any public FDOT meeting has the same format which was used on December 16th-- that format did not permit back and forth questions as an ordinary Zoom meeting would. As a result, there will be a GGPA Zoom meeting to which FDOT representatives are invited and questions can be asked by GGPA Board members and building liaisons. This meeting will take place on January 12, 2021 at 1 p.m. In preparation for that meeting, the GGPA asked FDOT to provide maps for each phase of construction applicable to entry and exit from Golden Gate Point. You can access all of the maps by clicking here,

The timing of each roundabout construction phase as shown in the maps are as follows:

Pre phase – 100 Days

Phase 1A – 100 Days

Phase 1B- 60 Days

Phase 2A – 90 Days

Phase 2B – 100 Days

If you have any questions after looking at these maps, please email your questions to the GGPA at goldengatepointassociation@gmail.com before January 12. We will ask those questions at the GGPA informational meeting. If you want to attend the Zoom meeting, please let us know and we'll see if we can manage additional participants on the Zoom call.